A global life sciences company identified more than $2 million in savings by transforming how spare parts were managed, purchased, and utilized — starting from what one stakeholder described as “zero control over MRO spend.”
Master MRO Data Cleansing
A life sciences company operated hundreds of sites, many without a centralized view of their MRO inventory.
In partnership with Procure Analytics’ Master Data Services, the company piloted a master MRO data cleansing and governance process at a single site.
Prior to the pilot:
- Materials at the pilot site were dispersed across storage locations.
- There was no standardized way to describe or track spare parts.
- In many cases, inventory levels were not updated, resulting in expedited purchases and, at times, production delays.
- The organization could not accurately assess its on-hand value, understand consumption patterns, or identify opportunities for cost reduction.
MRO Inventory Consolidation
The pilot began by consolidating MRO inventory. Materials previously scattered across multiple locations were moved into a central storeroom, creating a single point of access and control.
A formal material master was established, enabling consistent naming conventions and classification of parts. This provided the foundation for integration with IBM Maximo, allowing spare parts to be linked directly to assets and maintenance activities.
For the first time, the organization could begin to align inventory with actual operational needs.
At the same time, standardized processes were introduced for purchasing, receiving, issuing, and stocking materials.
The result was a fundamentally different way of managing MRO materials.
Reduced Material Spend and Administrative Burden
Now, with improved visibility into existing inventory, the organization is no longer buying parts it already owns. This has reduced material spend and the administrative burden associated with procurement:
- Parts that were once hidden or difficult to locate are now centrally available, enabling faster maintenance response times.
- Teams identified numerous parts tied to obsolete or decommissioned equipment.
- Instances where manufacturers had discontinued parts were uncovered, allowing the organization to proactively identify obsolescence risks.
- Inventory items that had expired or deteriorated were identified, reducing operational risk.
The transition from fragmented inventory management to a controlled, data-driven process created improved communication, greater accountability, and a stronger sense of operational ownership.
5x-7x Return on Investment
The pilot site is now positioned to capture significant measurable savings, including:
- Inventory reduction and working capital recovery: $1.25 million-$4 million
- Procurement savings (supplier consolidation, improved sourcing leverage): $400,000-$750,000
- Administrative efficiencies: $200,000-$375,000
- Maintenance efficiencies: $78,000
- Downtime avoidance: $250,000-$500,000
Even under conservative assumptions, the site is positioned to achieve a 5x-7x return on investment.